Appendix 1: Programme Update
Assisted Collections |
|
||||||
Project objectives |
Redesigning the Assisted Collection service to deliver improvements to residents and crews |
Overall RAG status (including explanation) |
Previous report |
This report |
|||
Green |
Green |
||||||
Project start date |
January 2022 |
Project end date |
September 2023 |
|
|||
Reporting period |
October 2022 to February 2023 |
Key planned activities |
Continue delivery of audit (in four phases) Carry out targeted H&S risk assessments for audited ACs Carry out data analysis Continue to deliver Action Plan |
|
|||
Key achievements since the last update |
Delivered training to Contact Centre Prepared and sent letters for test audit Reviewed test audit Begun definitive audit |
||||||
Key dependencies |
Customer experience Digital Cityclean Health & Safety Managing waste responsibly |
Key risks and issues |
Resources to deliver project |
|
|||
|
Blueprint to a circular economy |
|
||||||
Project objectives |
Creating a model to move towards a circular economy. Work package three – promote household behaviour change |
Overall RAG status (including explanation) |
Previous report |
This report |
|||
Amber |
Amber |
||||||
Project start date |
June 2021 |
Project end date |
June 2023 |
|
|||
Reporting period |
October 2022 to February 2023 |
Key planned activities |
Plan the fourth community pop up event, with a focus on recycling. Continue to recruit champions to promote behaviour change on reduce, reuse, repair and recycle. Continue to promote the MMM app to increase users across the city. Continue to promote the repair workshops and the LoTs scheme. |
|
|||
Held third community pop event on electrical waste on 29 October at the Revaluit Hub Continued to engage with Circular Economy Champions scheme via newly created WhatsApp group to share messages on reduce, reuse and recycle. Created material as part of second phase of school’s pilot where school children pledge sustainable actions following learning. Launched ‘Make Materials Matter’ pilot to encourage reduce, reuse, repair and recycle activities. It has been promoted to the 3500 current Move for Change users, with many of these also participating in the Make Materials Matter challenge. Held repair workshops (Circular Saturdays) covering: electrical disassembly, clothes mending, mosaic workshops, toy and clothes swap, knitting with plastic, tool maintenance and repair, wood finishing, and sock puppet making. Library of Things (LoTs) commissioned local partner to deliver scheme to loan high value items; 565 Brighton & Hove residents registered. Scheme delivered through the Revaluit shop and includes PAT testing on site |
|||||||
Key dependencies |
Customer experience Managing waste responsibly |
Key risks and issues |
Low attendance at events and take up of app, workshops and LoTs scheme. |
|
|||
|
Commercial bins on the highway |
|
||||||
Project objectives |
Creating and implementing a model to manage commercial bins on the highway across Brighton & Hove. |
Overall RAG status (including explanation) |
Previous report |
This report |
|||
Green |
Green |
||||||
Project start date |
September 2019 |
Project end date |
December 2022 |
|
|||
Reporting period |
October 2022 to February 2023 |
Key planned activities |
Continue to provide further advice and guidance. Seek permission to consult on Phase 2 and progress, if approved. |
|
|||
Key achievements since the last update |
Significant reduction of commercial bins on the highway across the T-Zone area. Reduced complaints about commercial bins on the highway. 1506 Fixed Penalty Notices issued (up to 2 February 2023). The number issued each week is reducing, demonstrating compliance. See chart 1 below. Council officers have met, and continue to meet, with local businesses on individual and group basis to offer further advice and guidance. Started planning for Phase 2, including consultation for additional roads to extend to. |
||||||
Key dependencies |
Customer experience Environmental enforcement Managing waste responsibly |
Key risks and issues |
Capacity of businesses and other stakeholders to follow new model National Resources & Waste Strategy |
|
|||
|
Chart 1: FPNs issued week-on-week
Communal bin system |
|
|||||||
Project objectives |
Implementing an improved communal bin service for recycling and refuse as appropriate across the city |
Overall RAG status (including explanation) |
Previous report |
This report |
||||
Amber |
Amber |
|||||||
Project start date |
June 2020 |
Project end date |
March 2024 |
|
||||
Reporting period |
October 2022 to February 2023 |
Key planned activities |
Trial side loading mixed recycling and glass bins. Complete final specifications document after agreeing all bin types Continue with consultations Advertise Traffic Regulation Orders (TROs) Commence resident engagement Agree bin assembly plan Agree implementation plan & schedule Begin procurement process |
|
||||
Key achievements since the last update |
Started consultation with relevant drivers and operatives on the different types of bins that have been trialled. Started consultation with relevant drivers and operatives on the proposed trial bin bay locations. Traffic Regulation Orders (TROs) prepared for advertising with plans drawn for each proposed bin bay location. |
|||||||
Key dependencies |
Traffic Regulation Orders (TROs) Round structures Procurement |
Key risks and issues |
Traffic Regulation Orders (TROs) Glass bins Funding |
|
||||
|
|
|||||||
Customer Experience |
|
|||||||
Project objectives |
Improving the customer experience and providing a consistent service to everyone who contacts Cityclean |
Overall RAG status (including explanation) |
Previous report |
This report |
||||
Green |
Green |
|||||||
Project start date |
April 2019 |
Project end date |
Ongoing |
|
||||
Reporting period |
October 2022 to February 2023 |
Key planned activities |
Further TROs compiled to address issues of persistent missed collection due to access issues. Continue to develop Standard Operating Procedures to support the above and provide consistent service Continue to train and develop team |
|
||||
Key achievements since the last update |
96.9% of Stage 1 Complaints responded to within 10 days with an average response of 3.4 days. 100% of all Stage 1 complaints responded to within 20 working days. Further ESA trained on responding to Stage 1 Complaints and one additional ESA trained on invoicing processes. ESAs continue to respond on average, a 24 to 48-hour response time to emails (working days). |
|||||||
Key dependencies |
Assisted Collections Digital Cityclean Graffiti reduction Increasing material for recycling Management Framework Managing waste responsibly |
Key risks and issues |
Loss of support for project Industrial action |
|
||||
|
|
|||||||
Digital Cityclean |
|
|||||||
Project objectives |
Modernising the service and supporting the wider programme of change through technology |
Overall RAG status (including explanation) |
Previous report |
This report |
||||
Amber |
Amber |
|||||||
Project start date |
June 2020 |
Project end date |
March 2024 |
|
||||
Reporting period |
October 2022 to February 2023 |
Key planned activities |
Work with Bartec to agree implementation plan Continue to engage with the workforce |
|
||||
Key achievements since the last update |
Finished the procurement process Awarded contract to Bartec Contract signed by Bartec Held kick-off meeting with Bartec Started preparing data for implementation, including the assisted collection audit |
|||||||
Key dependencies |
Assisted Collections Bulky waste service review Communal bin system Customer experience Managing waste responsibly |
Key risks and issues |
IT&D resources & capacity Implementation timescales Existing poor data Withdrawal of support from workforce or trade unions |
|
||||
|
|
|||||||
Fleet Strategy |
|
|||||||
Project objectives |
Delivering of a 10-year strategy and green procurement plan, providing cost and savings projections. The strategy includes the migration to new technology as it develops, such as hydrogen fuel cells, to reduce maintenance and carbon emissions |
Overall RAG status (including explanation) |
Previous report |
This report |
||||
Green |
Green |
|||||||
Project start date |
March 2022 |
Project end date |
March 2030 |
|||||
Reporting period |
October 2022 to February 2023 |
Key planned activities |
Expecting delivery of first new communal bin electric vehicle in April 2023 Improve drivers’ hours recording Provide training for Vision from FTA for managers in operations Review the CPC training |
|||||
Key achievements since the last update |
Depot charging infrastructure in place and working 15 electric vehicles in use in Cityclean 13 electric vehicles in use in other services |
|||||||
Key dependencies |
Communal bin system Customer experience Digital Cityclean Food waste Health & Safety Hollingdean Depot Managing waste responsibly Operator’s Licence Procurement review |
Key risks and issues |
Resources – both time and finance Power infrastructure implemented and available Competing priorities e.g. service delivery and modernisation and improvement work Brexit – vehicles purchased from Europe National Resources & Waste Strategy Delays with contracts |
|
||||
|
Flyering |
|
||||||
Project objectives |
Improving the flyering service by reviewing the flyering framework and extending the current flyering zones. |
Overall RAG status (including explanation) |
Previous report |
This report |
|||
Amber |
Amber |
||||||
Project start date |
March 2022 |
Project end date |
March 2023 |
||||
Reporting period |
October 2022 to February 2023 |
Key planned activities |
Print notices Attach and publish notices Monitor notices for 28 days after publishing for any objections Improve application form Implement online payment system |
||||
Key achievements since the last update |
Site visit and lampposts identified Terms and conditions drafted Privacy notice reviewed Flyering framework reviewed |
||||||
Key dependencies |
Environmental Enforcement Communications Print & Sign |
Key risks and issues |
Objections to Notices Resources - staff, and possibly budget |
|
|||
|
Food waste collections |
|
||||||
Project objectives |
Complete analysis of food waste options |
Overall RAG status (including explanation) |
Previous report |
This report |
|||
Amber |
Amber |
||||||
Project start date |
June 2021 |
Project end date |
June 2023 |
|
|||
Reporting period |
October 2022 to February 2023 |
Key planned activities |
Until further guidance is received from central government, it is not possible to progress the analysis fully. The guidance expected will outline whether burdens funding will be made available and whether any exceptions exist to the announced new duty to collect food waste on a weekly basis. |
|
|||
Key achievements since the last update |
Completed WRAP food waste data gathering exercise on the communal service Completed DEFRA survey on disposal arrangements Attended DEFRA waste reforms forum to understand requirements of food waste implementation and receive updates Secured funding for Project Manager post for food waste collections |
||||||
Key dependencies |
Communal bin system Fleet strategy Customer experience Procurement review |
Key risks and issues |
Consistency announcements on other materials Data availability Space availability at the depot, to accommodate the required number of vehicles in accordance with the operators’ licence. IVC capacity only seasonal, identification of an alternative Workforce resistance to change |
|
|||
|
Graffiti Reduction Strategy |
|
||||||
Project objectives |
Delivering the aims of Graffiti Reduction Strategy, reducing the amount of graffiti vandalism around Brighton & Hove |
Overall RAG status (including explanation) |
Previous report |
This report |
|||
Amber |
Amber |
||||||
Project start date |
November 2018 |
Project end date |
March 2023 |
|
|||
Reporting period |
October 2022 to February 2023 |
Key planned activities |
Develop programme of work with Transport and Probation Service for bus shelters Review and update Strategy and Action Plan Begin communication with graffiti artists for murals |
|
|||
Key achievements since the last update |
Held joint action day between Sussex Police and Environmental Enforcement. Continued programme of work for the Targeted Action Zones; 11 roads have been completed to date. Continued removal of graffiti from council owned properties. Continued issuing of Community Protection Warnings and Notices to businesses to ensure graffiti is removed from commercial properties. Positive action from Statutory Undertakers for graffiti removal and ongoing work. Implemented remedial action processes. Software reconfigured for remedial action to manage processes from referral to invoicing. Created graffiti database/log Continued community engagement activities, meeting with various LATs and Resident Associations to discuss partnership work. Continued working closely with Sussex Police and ongoing Joint Action Group Meetings. |
||||||
Key dependencies |
Customer experience Environmental enforcement Digital Cityclean |
Key risks and issues |
Commercial property owners and Statutory Undertakers do not comply with Community Protection Warnings Council owned property not maintained to recommended standard creating conflict Competing graffiti removal priorities and capacity in teams to implement |
|
|||
|
Health & Safety |
|
||||||
Project objectives |
Improving health & safety compliance and performance across City Environment Management |
Overall RAG status (including explanation) |
Previous report |
This report |
|||
Amber |
Amber |
||||||
Project start date |
January 2021 |
Project end date |
Ongoing |
|
|||
Reporting period |
October 2022 to February 2023 |
Key planned activities |
Implement new lone working technology Re-advertise for a City Parks H&S Officer to support further improvements in health and safety performance management Deliver City Parks manual handling training Create a training matrix for City Parks Update hand-arm-vibration and noise action plans Undertake further priority audits on a risk basis |
|
|||
Key achievements since the last update |
Prepared Cityclean PPE requirements and produced accompanying Standard Operating Procedure Delivered iHasco manual handling training for Cityclean frontline operations staff Reviewed City Parks’ risk assessments Implemented inspection/maintenance programme contract with COLAS for City Parks lighting Begun Refurbishment Programme of City Parks’ mess rooms Started parks and open spaces site safety inspections |
||||||
Key dependencies |
Assisted Collections Fleet Strategy Hollingdean Depot Management Framework Operator’s Licence Workstyles |
Key risks and issues |
Constantly emerging new priorities and risks e.g. incident investigation, union raised issues Ongoing need for modernisation of the service including health and safety performance management, with suitable and sufficient risk assessments backed up by a working, evidencable training matrix Health & Safety Executive interventions and recommendations Resources to deliver priorities |
|
|||
|
|
|||||||
Project objectives |
Completing a feasibility study into the costs of introducing a wider range of materials into the recycling stream at Hollingdean Materials Recovery Facility Preparing for the implementation of the Environment Act |
Overall RAG status (including explanation) |
Previous report |
This report |
|||
Green |
Amber (due to continuing delays on announcements regarding the Environment Act) |
||||||
Project start date |
January 2022 |
Project end date |
2027 |
|
|||
Reporting period |
October 2022 to February 2023 |
Key planned activities |
Continue preparations for the Environment Act and refine plans to be in a position to make a bid to the government for burdens funding |
|
|||
Key achievements since the last update |
Indications from the feasibility study are that to reconfigure the existing MRF to include the sorting of additional materials for recycling will require major infrastructure changes This will require a multimillion-pound investment and changes to the ways materials are collected from households The government has indicated that burdens funding will be available to local authorities that have to make changes to meet the requirements of the Environment Act. However, it is not known whether this funding will be 100% of the cost and are awaiting information from the government |
||||||
Key dependencies |
Customer experience Digital Cityclean Fleet Strategy Food waste Managing waste responsibly Operator’s Licence |
Key risks and issues |
Outcomes from National Resources & Waste Strategy consultation currently unknown Resources – both time and finance |
|
|||
|
|
|
|
|
|||
Management Framework |
|
||||||
Project objectives |
Improving management processes at Cityclean to ensure BHCC policies and processes are followed |
Overall RAG status (including explanation) |
Previous report |
This report |
|||
Amber |
Amber |
||||||
Project start date |
July 2022 |
Project end date |
Ongoing |
|
|||
Reporting period |
October 2022 to February 2023 |
Key planned activities |
Progress Standard Operating Procedures Continue service improvement plans in key areas of focus. Progress joint working between Street Cleansing and Transport. With the council’s recruitment team, adopt a more streamlined approach to seasonal recruitment. Complete mid-year reviews with staff. |
|
|||
Key achievements since the last update |
Established Strategy Group meetings with new management teams; areas of focus identified and plans in place to deliver improvements in these areas. Continued to develop Standard Operating Procedures for several areas. Completed 74% PDPs across CEM, including a 71% completion rate for Operations (Refuse & Recycling, Street Cleansing, Commercial and Environmental Enforcement). Majority of the workforce is manual and not office based, and it is a significant improvement on previous years. Continued to engage Trade Unions and staff as part of the Wellbeing Group. Onsite Physio is being offered and the uptake up is very good. Volunteers have received training in Mental Health First Aid. Comprehensive training programme delivered for Public Toilets staff. Agreed joint working between Street Cleansing Managers and Transport Managers to address key issues of leafing to reduce flooding and reduce weeds. |
||||||
Key dependencies |
Customer Experience Hollingdean Depot Managing Waste responsibly Operator’s Licence |
Key risks and issues |
Competing priorities, particularly maintaining frontline service delivery National Resources and Waste Strategy Withdrawal of support from workforce or Trade Unions |
|
|||
|
|
|
|
|
|||
Managing Waste Responsibly |
|
||||||
Project objectives |
Delivering an informative and educational campaign to assist residents, visitors, businesses and crews to dispose of waste responsibly |
Overall RAG status (including explanation) |
Previous report |
This report |
|||
Amber |
Amber |
||||||
Project start date |
February 2019 |
Project end date |
March 2024 |
|
|||
Reporting period |
October 2022 to February 2023 |
Key planned activities |
Commence Student Waste Project Plan delivery Prepare action plan following results of composition analysis |
|
|||
Key achievements since the last update |
Received report for recent composition analysis Shared proactive communications on a low waste Christmas Encouraged more recycling as part of National Recycle Week |
||||||
Key dependencies |
Commercial bins on the highway Communal bin system Customer experience Environmental enforcement Fleet replacement Food waste Digital Cityclean |
Key risks and issues |
Resources – both time and finance National Resources & Waste Strategy Other priorities; service delivery and modernisation and improvement work Brexit – materials end destinations |
|
Operator’s Licence |
|
||||||
Project objectives |
Maintaining the current standing of the BHCC Operator’s Licence |
Overall RAG status (including explanation) |
Previous report |
This report |
|||
Green |
Green |
||||||
Project start date |
September 2019 |
Project end date |
Ongoing |
|
|||
Reporting period |
October 2022 to February 2023 |
Key planned activities |
Create accident reduction programme |
||||
Key achievements since the last update |
Started development new KPI suite |
||||||
Key dependencies |
Fleet Strategy Health & Safety Hollingdean Depot Management Framework |
Key risks and issues |
Withdrawal of support from workforce or trade unions HSE (Health & Safety Executive) interventions and recommendations National Resources & Waste Strategy |
|
|||
|
Procurement Review |
|
||||||
Project objectives |
Improving the procurement and contract management in Cityclean to deliver value for money and comply with council policies and procedures |
Overall RAG status (including explanation) |
Previous report |
This report |
|||
Amber |
Amber |
||||||
Project start date |
June 2022 |
Project end date |
Ongoing |
|
|||
Reporting period |
October 2022 to February 2023 |
Key planned activities |
Begin review of textile recycling contract Support management and implementation of new integrated waste management software contract Support communal bin procurement project Support Fleet with future compliant procurement of spare vehicle parts and maintenance Support procurement of new fuel supply contact for depot Further refine and deliver programme of compliance across service Continue contract management of PPE contract, external recycling providers and toilet consumables suppliers |
|
|||
Key achievements since the last update |
Maintained regular contract management of key external suppliers, including clinical waste, carton recycling, textile recycling, public toilet consumables (ongoing regular contract meetings) Identified further areas of non-compliance in City Environment (ongoing) Supporting communal bin procurement process (ongoing) Frameworks set up for procurement for toilet consumables and grounds maintenance equipment Supported City Parks’ procurement of allotment booking software Supported compliant procurement of Christmas tree recycling contract |
||||||
Key dependencies |
Communal bin system Fleet Strategy Food waste |
Key risks and issues |
Competing priorities |
|
|||
|
|
|||||||
Project objectives |
Identifying a sustainable future for each public toilet site |
Overall RAG status (including explanation) |
Previous report |
This report |
|||
Amber |
Red |
||||||
Project start date |
July 2020 |
Project end date |
March 2024 |
|
|||
Reporting period |
October 2022 to February 2023 |
Key planned activities |
Continue staff recruitment for summer opening hours Start recruitment of Programme Manager to develop Public Toilet Plan |
|
|||
Recent updates |
Following the forecasted overspend, 10 sites which were closed in October 2022 remain closed. Started planning for reopening, which will be a phased approach as staff are recruited. |
||||||
Key dependencies |
Customer experience Procurement review Public toilets: refurbishment programme |
Key risks and issues |
Staffing levels Resources – both time and finance |
|
|||
|
Public toilets: refurbishment programme |
|
||||||
Project objectives |
Improving the city’s public toilets |
Overall RAG status (including explanation) |
Previous report |
This report |
|||
Amber |
Amber |
||||||
Project start date |
January 2022 |
Project end date |
2026 |
|
|||
Reporting period |
October 2022 to February 2023 |
Key planned activities |
Prepare sites for reopening in spring Design cleaning and staffing rotas for the refurbished sites |
|
|||
Key achievements since the last update |
Works started at Kings Esplanade, Daltons, Saltdean Undercliff and Station Road on 28 November 2022. |
||||||
Key dependencies |
Public toilets: future service delivery |
Key risks and issues |
Supply chain issues Cost of refurbishment exceeds agreed budget due to cost inflation Closure of sites for refurbishment may lead to complaints Contractor unable to maintain/recruit sufficient staffing levels Contractor not delivering on the agreed specification and/or timescales Unforeseen work issues may exceed agreed budget |
|
|||
|
Recycling point audit |
|
||||||
Project objectives |
Reviewing existing recycling point locations |
Overall RAG status (including explanation) |
Previous report |
This report |
|||
Green |
Green |
||||||
Project start date |
June 2022 |
Project end date |
June 2023 |
|
|||
Reporting period |
October 2022 to February 2023 |
Key planned activities |
Ongoing engagement with operations for proposed changes at sites Site visits with operations to assess best arrangement of bins |
|
|||
Key achievements since the last update |
Completed recycling point audit Started initial engagement with operations for changes to recycling points |
||||||
Key dependencies |
Improving the communal bin system Recycling Quality Assurance report for textile and cartons recycling Procurement of WEEE bins Food waste options |
Key risks and issues |
Budget restrictions Resident complaints Increased fly-tipping Graffiti and bin tagging |
|
|||
|
|
|
|
|
|||
Weed management |
|
||||||
Project objectives |
Implementing sustainable and cost-effective ways of managing weeds without the use of pesticides |
Overall RAG status (including explanation) |
Previous report |
This report |
|||
Amber |
Amber |
||||||
Project start date |
July 2019 |
Project end date |
March 2023 |
|
|||
Reporting period |
October 2022 to February 2023 |
Key planned activities |
Deliver weeding plan for 2023 Review and measure impact of the Plan to provide feedback and options for an ETS Committee Report in January 2024. Continue to assess alternative methods of weed removal Deliver proactive Communication plan. Continue joint working with City Transport |
|
|||
Key achievements since the last update |
Developed revised approach for 2023 weed removal using a traffic light system to target most affected areas causing access issues or damage to highway. Procured additional tools to assist with weed removal in 2023. Six additional staff recruited to focus on weeding. Started proactive communication plan for 2023 weeding season. Exploring joint working with City Transport on parking suspensions to enable Cityclean to use mechanical weed removal without risk to parked cars |
||||||
Key dependencies |
Customer experience |
Key risks and issues |
Competing priorities, particularly if posts not filled Lack of resources |
|
Workstyles |
|
||||||
Project objectives |
Creating new office space at Hollingdean Depot, incorporating Workstyles principles |
Overall RAG status (including explanation) |
Previous report |
This report |
|||
Amber |
Amber |
||||||
Project start date |
November 2019 |
Project end date |
TBC |
|
|||
Reporting period |
October 2022 to February 2023 |
Key planned activities |
Continue with plans for new building Relocation of server room complete |
|
|||
Key achievements since the last update |
Completed new building plans Surveys completed Started server room relocation Started preparing report for Policy & Resources Committee |
||||||
Key dependencies |
Health & Safety Hollingdean Depot |
Key risks and issues |
Staff working in portacabins which are coming to end of life and do not provide sufficient space, exacerbated since the pandemic Resources – both time and finance |
|
|||
|