Appendix 1: Programme Update

Assisted Collections

 

Project objectives

Redesigning the Assisted Collection service to deliver improvements to residents and crews

Overall RAG status (including explanation)

Previous report

This report

Green

Green

Project start date

January 2022

Project end date

September 2023

 

Reporting period

October 2022 to February 2023

Key planned activities

Continue delivery of audit (in four phases)

Carry out targeted H&S risk assessments for audited ACs

Carry out data analysis

Continue to deliver Action Plan

 

Key achievements since the last update

Delivered training to Contact Centre

Prepared and sent letters for test audit

Reviewed test audit

Begun definitive audit

Key dependencies

Customer experience

Digital Cityclean

Health & Safety

Managing waste responsibly

Key risks and issues

Resources to deliver project

 

 

 

Blueprint to a circular economy

 

Project objectives

Creating a model to move towards a circular economy. Work package three – promote household behaviour change

Overall RAG status (including explanation)

Previous report

This report

Amber

Amber

Project start date

June 2021

Project end date

June 2023

 

Reporting period

October 2022 to February 2023

Key planned activities

Plan the fourth community pop up event, with a focus on recycling. 

Continue to recruit champions to promote behaviour change on reduce, reuse, repair and recycle.

Continue to promote the MMM app to increase users across the city.

Continue to promote the repair workshops and the LoTs scheme.

 

Key achievements since the last update

Held third community pop event on electrical waste on 29 October at the Revaluit Hub

Continued to engage with Circular Economy Champions scheme via newly created WhatsApp group to share messages on reduce, reuse and recycle. Created material as part of second phase of school’s pilot where school children pledge sustainable actions following learning.

Launched ‘Make Materials Matter’ pilot to encourage reduce, reuse, repair and recycle activities. It has been promoted to the 3500 current Move for Change users, with many of these also participating in the Make Materials Matter challenge.  

Held repair workshops (Circular Saturdays) covering: electrical disassembly, clothes mending, mosaic workshops, toy and clothes swap, knitting with plastic, tool maintenance and repair, wood finishing, and sock puppet making.

Library of Things (LoTs) commissioned local partner to deliver scheme to loan high value items; 565 Brighton & Hove residents registered. Scheme delivered through the Revaluit shop and includes PAT testing on site

Key dependencies

Customer experience

Managing waste responsibly

Key risks and issues

Low attendance at events and take up of app, workshops and LoTs scheme.

 

 

 

Commercial bins on the highway

 

Project objectives

Creating and implementing a model to manage commercial bins on the highway across Brighton & Hove.

Overall RAG status (including explanation)

Previous report

This report

Green

Green

Project start date

September 2019

Project end date

December 2022

 

Reporting period

October 2022 to February 2023

Key planned activities

Continue to provide further advice and guidance.

Seek permission to consult on Phase 2 and progress, if approved.

 

Key achievements since the last update

Significant reduction of commercial bins on the highway across the T-Zone area.

Reduced complaints about commercial bins on the highway.

1506 Fixed Penalty Notices issued (up to 2 February 2023). The number issued each week is reducing, demonstrating compliance. See chart 1 below.

Council officers have met, and continue to meet, with local businesses on individual and group basis to offer further advice and guidance.

Started planning for Phase 2, including consultation for additional roads to extend to.

Key dependencies

Customer experience

Environmental enforcement

Managing waste responsibly

Key risks and issues

Capacity of businesses and other stakeholders to follow new model

National Resources & Waste Strategy

 

 

 

Chart 1: FPNs issued week-on-week

Timeline  Description automatically generated with medium confidence 

 

 

 

 

 

 

 

 

 


Communal bin system

 

Project objectives

Implementing an improved communal bin service for recycling and refuse as appropriate across the city

Overall RAG status (including explanation)

Previous report

This report

Amber

Amber

Project start date

June 2020

Project end date

March 2024

 

Reporting period

October 2022 to February 2023

Key planned activities

Trial side loading mixed recycling and glass bins.

Complete final specifications document after agreeing all bin types

Continue with consultations

Advertise Traffic Regulation Orders (TROs)

Commence resident engagement

Agree bin assembly plan

Agree implementation plan & schedule

Begin procurement process

 

Key achievements since the last update

Started consultation with relevant drivers and operatives on the different types of bins that have been trialled.

Started consultation with relevant drivers and operatives on the proposed trial bin bay locations.

Traffic Regulation Orders (TROs) prepared for advertising with plans drawn for each proposed bin bay location.

Key dependencies

Traffic Regulation Orders (TROs)

Round structures

Procurement

Key risks and issues

Traffic Regulation Orders (TROs)

Glass bins

Funding

 

 

 

Customer Experience

 

Project objectives

Improving the customer experience and providing a consistent service to everyone who contacts Cityclean

Overall RAG status (including explanation)

Previous report

This report

Green

Green

Project start date

April 2019

Project end date

Ongoing

 

Reporting period

October 2022 to February 2023

Key planned activities

Further TROs compiled to address issues of persistent missed collection due to access issues.

Continue to develop Standard Operating Procedures to support the above and provide consistent service

Continue to train and develop team

 

Key achievements since the last update

96.9% of Stage 1 Complaints responded to within 10 days with an average response of 3.4 days. 100% of all Stage 1 complaints responded to within 20 working days.

Further ESA trained on responding to Stage 1 Complaints and one additional ESA trained on invoicing processes.

ESAs continue to respond on average, a 24 to 48-hour response time to emails (working days).

Key dependencies

Assisted Collections

Digital Cityclean

Graffiti reduction

Increasing material for recycling

Management Framework

Managing waste responsibly

Key risks and issues

Loss of support for project

Industrial action

 

 

 

Digital Cityclean

 

Project objectives

Modernising the service and supporting the wider programme of change through technology

Overall RAG status (including explanation)

Previous report

This report

Amber

Amber

Project start date

June 2020

Project end date

March 2024

 

Reporting period

October 2022 to February 2023

Key planned activities

Work with Bartec to agree implementation plan

Continue to engage with the workforce

 

Key achievements since the last update

Finished the procurement process

Awarded contract to Bartec

Contract signed by Bartec

Held kick-off meeting with Bartec

Started preparing data for implementation, including the assisted collection audit

Key dependencies

Assisted Collections

Bulky waste service review

Communal bin system

Customer experience

Managing waste responsibly

Key risks and issues

IT&D resources & capacity

Implementation timescales

Existing poor data

Withdrawal of support from workforce or trade unions

 

 

 

Fleet Strategy

 

Project objectives

Delivering of a 10-year strategy and green procurement plan, providing cost and savings projections. The strategy includes the migration to new technology as it develops, such as hydrogen fuel cells, to reduce maintenance and carbon emissions

Overall RAG status (including explanation)

Previous report

This report

Green

Green

Project start date

March 2022

Project end date

March 2030

Reporting period

October 2022 to February 2023

Key planned activities

Expecting delivery of first new communal bin electric vehicle in April 2023

Improve drivers’ hours recording

Provide training for Vision from FTA for managers in operations

Review the CPC training

Key achievements since the last update

Depot charging infrastructure in place and working

15 electric vehicles in use in Cityclean

13 electric vehicles in use in other services

Key dependencies

Communal bin system

Customer experience

Digital Cityclean

Food waste

Health & Safety

Hollingdean Depot

Managing waste responsibly

Operator’s Licence

Procurement review

Key risks and issues

Resources – both time and finance

Power infrastructure implemented and available

Competing priorities e.g. service delivery and modernisation and improvement work

Brexit – vehicles purchased from Europe

National Resources & Waste Strategy

Delays with contracts

 

 

 

Flyering

 

Project objectives

Improving the flyering service by reviewing the flyering framework and extending the current flyering zones.

Overall RAG status (including explanation)

Previous report

This report

Amber

Amber

Project start date

March 2022

Project end date

March 2023

Reporting period

October 2022 to February 2023

Key planned activities

Print notices

Attach and publish notices

Monitor notices for 28 days after publishing for any objections

Improve application form

Implement online payment system

Key achievements since the last update

Site visit and lampposts identified

Terms and conditions drafted

Privacy notice reviewed

Flyering framework reviewed

Key dependencies

Environmental Enforcement

Communications

Print & Sign

Key risks and issues

Objections to Notices

Resources - staff, and possibly budget

 

 

 

Food waste collections

 

Project objectives

Complete analysis of food waste options

Overall RAG status (including explanation)

Previous report

This report

Amber

Amber

Project start date

June 2021

Project end date

June 2023

 

Reporting period

October 2022 to February 2023

Key planned activities

Until further guidance is received from central government, it is not possible to progress the analysis fully. The guidance expected will outline whether burdens funding will be made available and whether any exceptions exist to the announced new duty to collect food waste on a weekly basis.

 

Key achievements since the last update

Completed WRAP food waste data gathering exercise on the communal service

Completed DEFRA survey on disposal arrangements 

Attended DEFRA waste reforms forum to understand requirements of food waste implementation and receive updates

Secured funding for Project Manager post for food waste collections

Key dependencies

Communal bin system

Fleet strategy

Customer experience

Procurement review

Key risks and issues

Consistency announcements on other materials 

Data availability

Space availability at the depot, to accommodate the required number of vehicles in accordance with the operators’ licence.

IVC capacity only seasonal, identification of an alternative

Workforce resistance to change

 

 

 

Graffiti Reduction Strategy

 

Project objectives

Delivering the aims of Graffiti Reduction Strategy, reducing the amount of graffiti vandalism around Brighton & Hove

Overall RAG status (including explanation)

Previous report

This report

Amber

Amber

Project start date

November 2018

Project end date

March 2023

 

Reporting period

October 2022 to February 2023

Key planned activities

Develop programme of work with Transport and Probation Service for bus shelters

Review and update Strategy and Action Plan

Begin communication with graffiti artists for murals

 

Key achievements since the last update

Held joint action day between Sussex Police and Environmental Enforcement.

Continued programme of work for the Targeted Action Zones; 11 roads have been completed to date.

Continued removal of graffiti from council owned properties.

Continued issuing of Community Protection Warnings and Notices to businesses to ensure graffiti is removed from commercial properties.

Positive action from Statutory Undertakers for graffiti removal and ongoing work.

Implemented remedial action processes.

Software reconfigured for remedial action to manage processes from referral to invoicing.

Created graffiti database/log

Continued community engagement activities, meeting with various LATs and Resident Associations to discuss partnership work. 

Continued working closely with Sussex Police and ongoing Joint Action Group Meetings.

Key dependencies

Customer experience

Environmental enforcement

Digital Cityclean

Key risks and issues

Commercial property owners and Statutory Undertakers do not comply with Community Protection Warnings

Council owned property not maintained to recommended standard creating conflict

Competing graffiti removal priorities and capacity in teams to implement

 

 

 

Health & Safety

 

Project objectives

Improving health & safety compliance and performance across City Environment Management

Overall RAG status (including explanation)

Previous report

This report

Amber

Amber

Project start date

January 2021

Project end date

Ongoing

 

Reporting period

October 2022 to February 2023

Key planned activities

Implement new lone working technology

Re-advertise for a City Parks H&S Officer to support further improvements in health and safety performance management

Deliver City Parks manual handling training

Create a training matrix for City Parks

Update hand-arm-vibration and noise action plans

Undertake further priority audits on a risk basis

 

Key achievements since the last update

Prepared Cityclean PPE requirements and produced accompanying Standard Operating Procedure

Delivered iHasco manual handling training for Cityclean frontline operations staff

Reviewed City Parks’ risk assessments

Implemented inspection/maintenance programme contract with COLAS for City Parks lighting

Begun Refurbishment Programme of City Parks’ mess rooms

Started parks and open spaces site safety inspections

Key dependencies

Assisted Collections

Fleet Strategy

Hollingdean Depot

Management Framework

Operator’s Licence

Workstyles

Key risks and issues

Constantly emerging new priorities and risks e.g. incident investigation, union raised issues

Ongoing need for modernisation of the service including health and safety performance management, with suitable and sufficient risk assessments backed up by a working, evidencable training matrix

Health & Safety Executive interventions and recommendations

Resources to deliver priorities

 

 

 

Increasing material for recycling

 

Project objectives

Completing a feasibility study into the costs of introducing a wider range of materials into the recycling stream at Hollingdean Materials Recovery Facility Preparing for the implementation of the Environment Act

Overall RAG status (including explanation)

Previous report

This report

Green

Amber (due to continuing delays on announcements regarding the Environment Act)

Project start date

January 2022

Project end date

2027

 

Reporting period

October 2022 to February 2023

Key planned activities

Continue preparations for the Environment Act and refine plans to be in a position to make a bid to the government for burdens funding

 

Key achievements since the last update

Indications from the feasibility study are that to reconfigure the existing MRF to include the sorting of additional materials for recycling will require major infrastructure changes

This will require a multimillion-pound investment and changes to the ways materials are collected from households

The government has indicated that burdens funding will be available to local authorities that have to make changes to meet the requirements of the Environment Act. However, it is not known whether this funding will be 100% of the cost and are awaiting information from the government

Key dependencies

Customer experience

Digital Cityclean

Fleet Strategy

Food waste

Managing waste responsibly

Operator’s Licence

Key risks and issues

Outcomes from National Resources & Waste Strategy consultation currently unknown

Resources – both time and finance

 

 

 

 

 

 

Management Framework

 

Project objectives

Improving management processes at Cityclean to ensure BHCC policies and processes are followed

Overall RAG status (including explanation)

Previous report

This report

Amber

Amber

Project start date

July 2022

Project end date

Ongoing

 

Reporting period

October 2022 to February 2023

Key planned activities

 

Progress Standard Operating Procedures

Continue service improvement plans in key areas of focus.

Progress joint working between Street Cleansing and Transport.

With the council’s recruitment team, adopt a more streamlined approach to seasonal recruitment.

Complete mid-year reviews with staff.

 

Key achievements since the last update

Established Strategy Group meetings with new management teams; areas of focus identified and plans in place to deliver improvements in these areas.

Continued to develop Standard Operating Procedures for several areas.

Completed 74% PDPs across CEM, including a 71% completion rate for Operations (Refuse & Recycling, Street Cleansing, Commercial and Environmental Enforcement).  Majority of the workforce is manual and not office based, and it is a significant improvement on previous years. 

Continued to engage Trade Unions and staff as part of the Wellbeing Group. Onsite Physio is being offered and the uptake up is very good. Volunteers have received training in Mental Health First Aid.

Comprehensive training programme delivered for Public Toilets staff.

Agreed joint working between Street Cleansing Managers and Transport Managers to address key issues of leafing to reduce flooding and reduce weeds.

Key dependencies

Customer Experience

Hollingdean Depot

Managing Waste responsibly

Operator’s Licence

Key risks and issues

Competing priorities, particularly maintaining frontline service delivery

National Resources and Waste Strategy

Withdrawal of support from workforce or Trade Unions

 

 

 

 

 

 

Managing Waste Responsibly

 

Project objectives

Delivering an informative and educational campaign to assist residents, visitors, businesses and crews to dispose of waste responsibly

Overall RAG status (including explanation)

Previous report

This report

Amber

Amber

Project start date

February 2019

Project end date

March 2024

 

Reporting period

October 2022 to February 2023

Key planned activities

Commence Student Waste Project Plan delivery

Prepare action plan following results of composition analysis

 

Key achievements since the last update

Received report for recent composition analysis

Shared proactive communications on a low waste Christmas

Encouraged more recycling as part of National Recycle Week

Key dependencies

Commercial bins on the highway

Communal bin system

Customer experience

Environmental enforcement

Fleet replacement

Food waste

Digital Cityclean

Key risks and issues

Resources – both time and finance

National Resources & Waste Strategy

Other priorities; service delivery and modernisation and improvement work

Brexit – materials end destinations

 

 

Operator’s Licence

 

Project objectives

Maintaining the current standing of the BHCC Operator’s Licence

Overall RAG status (including explanation)

Previous report

This report

Green

Green

Project start date

September 2019

Project end date

Ongoing

 

Reporting period

October 2022 to February 2023

Key planned activities

Create accident reduction programme

Key achievements since the last update

Started development new KPI suite

Key dependencies

Fleet Strategy

Health & Safety

Hollingdean Depot

Management Framework

Key risks and issues

Withdrawal of support from workforce or trade unions

HSE (Health & Safety Executive) interventions and recommendations

National Resources & Waste Strategy

 

 

 

Procurement Review

 

Project objectives

Improving the procurement and contract management in Cityclean to deliver value for money and comply with council policies and procedures

Overall RAG status (including explanation)

Previous report

This report

Amber

Amber

Project start date

June 2022

Project end date

Ongoing

 

Reporting period

October 2022 to February 2023

Key planned activities

Begin review of textile recycling contract

Support management and implementation of new integrated waste management software contract

Support communal bin procurement project

Support Fleet with future compliant procurement of spare vehicle parts and maintenance

Support procurement of new fuel supply contact for depot

Further refine and deliver programme of compliance across service

Continue contract management of PPE contract, external recycling providers and toilet consumables suppliers

 

Key achievements since the last update

Maintained regular contract management of key external suppliers, including clinical waste, carton recycling, textile recycling, public toilet consumables (ongoing regular contract meetings)

Identified further areas of non-compliance in City Environment (ongoing)

Supporting communal bin procurement process (ongoing)

Frameworks set up for procurement for toilet consumables and grounds maintenance equipment

Supported City Parks’ procurement of allotment booking software

Supported compliant procurement of Christmas tree recycling contract

Key dependencies

Communal bin system

Fleet Strategy

Food waste

Key risks and issues

Competing priorities

 

 

 

Public toilets: service options

 

Project objectives

Identifying a sustainable future for each public toilet site

Overall RAG status (including explanation)

Previous report

This report

Amber

Red

Project start date

July 2020

Project end date

March 2024

 

Reporting period

October 2022 to February 2023

Key planned activities

Continue staff recruitment for summer opening hours

Start recruitment of Programme Manager to develop Public Toilet Plan

 

Recent updates

Following the forecasted overspend, 10 sites which were closed in October 2022 remain closed.

Started planning for reopening, which will be a phased approach as staff are recruited.

Key dependencies

Customer experience

Procurement review

Public toilets: refurbishment programme

Key risks and issues

Staffing levels

Resources – both time and finance

 

 

 

Public toilets: refurbishment programme

 

Project objectives

Improving the city’s public toilets

Overall RAG status (including explanation)

Previous report

This report

Amber

Amber

Project start date

January 2022

Project end date

2026

 

Reporting period

October 2022 to February 2023

Key planned activities

Prepare sites for reopening in spring

Design cleaning and staffing rotas for the refurbished sites

 

Key achievements since the last update

Works started at Kings Esplanade, Daltons, Saltdean Undercliff and Station Road on 28 November 2022.

Key dependencies

Public toilets: future service delivery

Key risks and issues

Supply chain issues

Cost of refurbishment exceeds agreed budget due to cost inflation

Closure of sites for refurbishment may lead to complaints

Contractor unable to maintain/recruit sufficient staffing levels

Contractor not delivering on the agreed specification and/or timescales

Unforeseen work issues may exceed agreed budget

 

 

 

Recycling point audit

 

Project objectives

Reviewing existing recycling point locations

Overall RAG status (including explanation)

Previous report

This report

Green

Green

Project start date

June 2022

Project end date

June 2023

 

Reporting period

October 2022 to February 2023

Key planned activities

Ongoing engagement with operations for proposed changes at sites

Site visits with operations to assess best arrangement of bins

 

Key achievements since the last update

Completed recycling point audit

Started initial engagement with operations for changes to recycling points

Key dependencies

Improving the communal bin system

Recycling Quality Assurance report for textile and cartons recycling

Procurement of WEEE bins

Food waste options

Key risks and issues

Budget restrictions

Resident complaints

Increased fly-tipping

Graffiti and bin tagging

 

 

 

 

 

 

Weed management

 

Project objectives

Implementing sustainable and cost-effective ways of managing weeds without the use of pesticides

Overall RAG status (including explanation)

Previous report

This report

Amber

Amber

Project start date

July 2019

Project end date

March 2023

 

Reporting period

October 2022 to February 2023

Key planned activities

Deliver weeding plan for 2023

Review and measure impact of the Plan to provide feedback and options for an ETS Committee Report in January 2024.

Continue to assess alternative methods of weed removal

Deliver proactive Communication plan.

Continue joint working with City Transport

 

Key achievements since the last update

Developed revised approach for 2023 weed removal using a traffic light system to target most affected areas causing access issues or damage to highway.

Procured additional tools to assist with weed removal in 2023.

Six additional staff recruited to focus on weeding.

Started proactive communication plan for 2023 weeding season.

Exploring joint working with City Transport on parking suspensions to enable Cityclean to use mechanical weed removal without risk to parked cars

Key dependencies

Customer experience

Key risks and issues

Competing priorities, particularly if posts not filled

Lack of resources

 

 

Workstyles

 

Project objectives

Creating new office space at Hollingdean Depot, incorporating Workstyles principles

Overall RAG status (including explanation)

Previous report

This report

Amber

Amber

Project start date

November 2019

Project end date

TBC

 

Reporting period

October 2022 to February 2023

Key planned activities

Continue with plans for new building

Relocation of server room complete

 

Key achievements since the last update

Completed new building plans

Surveys completed

Started server room relocation

Started preparing report for Policy & Resources Committee

Key dependencies

Health & Safety

Hollingdean Depot

Key risks and issues

Staff working in portacabins which are coming to end of life and do not provide sufficient space, exacerbated since the pandemic

Resources – both time and finance